• BEM Practice
  • 9 min read
  • By Ir Vimal

Owners often ask whether a second engineer should look at a design before construction, or after a defect appears. Board of Engineers Malaysia (BEM) Circular No. 010, Checking / Reviewing the Work of Another Engineer (Rev 2, 1.4.2021), sets out when that is appropriate, who may do it, and how responsibility is shared with the First Engineer. Every point below comes from Circular 010 and the statutory provisions it cites. It is general information, not legal advice.

Key takeaways

  1. BEM distinguishes checking (usually authority-driven), reviewing (usually client-driven) and inspection of completed buildings (Circular 010, para 3.2).
  2. For design-stage checking, the checker is typically an Accredited Checker or a Professional Engineer with Practising Certificate (PEPC) of equivalent experience and discipline (para 5.5.1).
  3. Checking/reviewing must not become supplanting under Regulation 31. The checker must be invited, must not canvass, and the First Engineer must be informed (paras 4.1–4.2, 4.5).
  4. The checker/reviewer is responsible for the integrity of their own work within the agreed scope; implementing recommendations still needs a clear decision path with the First Engineer and the client (paras 4.3–4.4).
  5. Agree the check category (A / B / C) and terms of reference in writing before work starts (paras 3.2–3.3).
Quick answer

Checking engineer design Malaysia guide: when owners need a BEM Circular 010 check or review, roles, liability, appointment and common mistakes.

01Why owners ask for a check

Circular 010 notes that as works grow more complex, calls for checking or reviewing come from authorities and from owners (para 1.5). It is written mainly for civil engineering safety of buildings and slopes, but applies where appropriate to other disciplines (para 1.4).

Paragraph 2.1 says statutory checks under the Street, Drainage and Building Act 1974 (Act 133) focus on safety and stability, while owners may also want a second look at other aspects. An independent check can increase confidence for a comparatively small additional cost. By default the Checker/Reviewer covers permanent works deliverables only, unless the client extends scope to temporary works or supervision (para 1.6).

02Checking, reviewing and inspection

Paragraph 3.2 of Circular 010 defines three different activities:

TermTypical stageWho usually calls for it
CheckingDesign and/or constructionLocal authorities under their statutory powers
ReviewingDesign and/or constructionThe client
InspectionCompleted projects already in useThe owner, or by local-authority order

Inspection of as-built structures after occupation is treated separately in para 4.6. It may include recommending remedial design. It can only be performed by a PEPC who has no professional, financial or conflict of interest in the building. The inspector need not obtain the First Engineer’s consent, but may request information, and the First Engineer should not unreasonably withhold information needed to study defective works (para 4.6).

Financial and insurance organisations may also require due diligence or independent design checking on major projects (para 4.7).

03Three check categories (A, B and C)

Circular 010, para 3.2, sets out three categories so that the client and First Engineer can agree the depth of work:

AspectCategory A (Checker)Category B (Reviewer)Category C (Others)
AnalysisIndependent analysis, same or different methodologyUses the First Engineer’s submitted analysisNo separate independent analysis
DesignSeparate independent design checkVerify submitted analysis; no separate independent designNo independent design check of the First Designer’s submission
DeliverablesCheck all drawings and specificationsCheck/review all drawings and specificationsReview all drawings and specifications
ReportReport on independent analysis and design; comment on completenessReport findings on submitted analysis and design; comment on completenessComment on completeness of report, drawings and specifications
ConstructabilityComment based on experience and judgementComment based on experience and judgementComment based on experience and judgement
OutcomeHighlight weaknesses, errors, omissions, amendments neededSame as A for design documentsHighlight errors, omissions and corrections in drawings and documents

Paragraph 3.3 says the scope of Checker or Reviewer can be interchangeable and must be set in the Terms of Reference and appointment letter. The category should be agreed by all parties so that responsibilities, reporting and certification are clear.

On scope limits, para 5.10 adds that checking is restricted to the items indicated in Table A; checkers must not suggest alternative designs. Reviewers assess the First Engineer’s design based on Table A unless the owner’s terms of reference allow alternatives. If a Reviewer suggests an alternative, the merits must be justified and the First Engineer must be given a chance to comment.

Note: the category A/B/C summary above is taken from the para 3.2 narrative in Circular 010. The detailed Table A grid in the PDF extract used for this draft was not legible cell-by-cell, so individual Table A cells are not quoted.

04Who may check, review or inspect

For checking at design stage, para 5.5.1 says it should be carried out by an Accredited Checker or a PEPC with equivalent experience and of the appropriate discipline, other than where Act 133 already stipulates otherwise.

Paragraph 5.6 stresses that an engineer who accepts appointment as Checker, Reviewer or Inspector automatically assumes liabilities to the extent indicated in Table A.

Working principles in para 4.5 say an Accredited Checker or PEPC may check or review another engineer’s work only if invited without canvassing; the First Engineer has been informed in writing; the work stays within competence; integrity and decorum are maintained; the First Engineer’s reputation is not maliciously injured; scope is clear in the terms of reference; suggestions stay within applicable standards and by-laws; and the checker takes full responsibility for the integrity of the report.

05How to appoint without breaching Regulation 31

Circular 010, para 4.1, warns that checking or reviewing must not become intervening or taking over another engineer’s work within the meaning of Regulation 31 of the Registration of Engineers Regulations 1990 (Revised 2015).

Regulation 31 (Appendix II to the circular) prohibits a registered Engineer or Engineering Consultancy Practice from, directly or indirectly:

  • (a) supplanting or attempting to supplant another;
  • (b) intervening in work already entrusted to another; or
  • (c) taking over that work for the same client unless consent is obtained, or the client has formally notified that the other engineer’s services have been terminated in accordance with the contract (with a Board-stakeholder route for fee disputes).

Paragraph 4.2 is the owner’s practical safeguard. The client’s right to call for a check must not be exploited to obtain an assignment under the pretext of “value engineering”. If the check is undertaken at the client’s invitation, without canvassing or touting, and with the First Engineer’s prior knowledge, Regulation 31 is not deemed contravened.

In practice: put the request in writing, tell the First Engineer who is appointed and on what scope, keep the terms of reference, and do not ask a second engineer to redesign the scheme behind the First Engineer’s back.

06Responsibility when recommendations conflict

Paragraph 4.3 says the exact line between checker/reviewer and First Engineer is hard to draw, but the guiding principle is that the checker/reviewer is responsible for the professional integrity, thoroughness and competence of his own work within the engagement.

Paragraph 4.4 then sets decision paths after discussion with all parties:

  • 4.4.1 – Client implements recommendations with the First Engineer’s agreement. The First Engineer incorporates amendments, submits for approval, endorses them and bears full responsibility; if he also supervises construction, he remains responsible for works to approved plans.
  • 4.4.2 – Client insists over the First Engineer’s objections and may omit that portion of the works. The First Engineer should obtain a client omission/indemnity letter, recover fees for work done, and the engineer taking over follows Circular No. 008. If recommendations are unacceptable and unsafe, the First Engineer may withdraw as Submitting Engineer.
  • 4.4.3 – Client rejects the Checker/Reviewer’s recommendations on the First Engineer’s objection, which imposes higher liability on the First Engineer for defects pointed out by the checker.
  • 4.4.4 – Client may engage a second checker acceptable to both; those findings feed back into 4.4.1–4.4.3.

07Statutory triggers owners should know

Circular 010 points to Act 133 provisions that already force a second pair of eyes in defined cases (Appendix I):

  • Section 70(2)(c) – for erection involving a slope steeper than 25 degrees and total vertical height more than 10 metres, a geotechnical report must be submitted and verified by an Accredited Checker registered with BEM.
  • Section 70B – if the local authority reasonably suspects a defect, deformation or deterioration in a building under erection that may result in failure, it may order the owner to review safety and stability of the building, foundation and surroundings. Under section 70B(3), that review must be by a qualified person other than the person who prepared and certified the original plans and calculations.

These are statutory routes. Owners can still commission a voluntary review under Circular 010 for other reasons, using the appointment rules above.

08Common mistakes we see

  1. Appointing a checker without telling the First Engineer. That risks looking like intervention under Regulation 31. Circular 010 expects documentary evidence that the First Engineer has been informed (para 4.5(b)).
  2. Leaving the check category undefined. Without an agreed A/B/C category and terms of reference, disputes later turn on what the checker was supposed to do (para 3.3).
  3. Treating a Category B review as a full independent redesign. Category B does not require separate independent design (para 3.2).
  4. Assuming the checker automatically takes design liability for the whole project. The First Engineer who adopts amendments under para 4.4.1 endorses and bears full responsibility for what he submits.
  5. Using “value engineering” approaches that canvassed the client. Paragraph 4.2 warns against exploiting the client’s prerogative to obtain work by canvassing or touting.

Frequently asked questions

Does every building project in Malaysia need a design checker?

No. Circular 010 recognises statutory checks under Act 133 and voluntary checks or reviews called by the client or other stakeholders. There is no general rule in Circular 010 that every project must have a checker.

Can I appoint any Professional Engineer as checker?

For design-stage checking, para 5.5.1 points to an Accredited Checker or a PEPC of equivalent experience and appropriate discipline (subject to Act 133 where it already applies). The appointee must also stay within competence (para 4.5(c)).

Do I need the First Engineer's consent for a post-occupation inspection?

For inspection of as-built structures under para 4.6, the PEPC inspector engaged by the owner is under no obligation to obtain the First Engineer’s consent, but may request information.

What if my First Engineer disagrees with the checker?

Follow the discussion paths in paras 4.4.1–4.4.4. Options include adoption with First Engineer endorsement, omission and takeover under Circular 008, rejection of the checker’s recommendations (with higher liability on the First Engineer), or a second checker acceptable to both.

Does a check cover temporary works?

By default, no. Paragraph 1.6 limits responsibility to permanent-works deliverables unless the client extends the scope to temporary works or supervision.

Is Circular 010 only for civil and structural work?

It is intended mainly for civil engineering safety of buildings and slopes, but para 1.4 says it applies where appropriate to other disciplines.

References

  1. [1] BEM Circular No. 010 – Checking / Reviewing the Work of Another Engineer, Rev 2 (1.4.2021): https://bem.org.my/uploads/ISO/ProfessionalPractice/f9c4b5ab782916ee2479eeb18fd8a0e8.pdf
  2. [2] BEM – Circulars and Guidelines index: https://bem.org.my/Landing/viewPPDetail/3
  3. [3] Street, Drainage and Building Act 1974 (Act 133), sections 70(2)(c) and 70B (as reproduced in Circular 010 Appendix I)
  4. [4] Registration of Engineers Regulations 1990 (Revised 2015), Regulation 31 (as reproduced in Circular 010 Appendix II)
  5. [5] Registration of Engineers Act 1967 (Revised 2015) – Accredited Checker provisions referenced in Circular 010 para 1.1
Pro Inspect Solution logo

Written byIr Vimal

Leads building inspection, concrete assessment and defect investigation work at Pro Inspect Solution, and writes guidance for owners, JMBs/MCs, developers, contractors and engineers. LinkedIn

Questions about an independent engineering inspection?

Contact Pro Inspect Solution on WhatsApp or call +60 16-806 4902. Email inspectsolution.pro@gmail.com