Introduction
Kwasa Damansara is a master-planned township on the former Rubber Research Institute land in north-west Klang Valley. The master developer is Kwasa Land Sdn Bhd, a wholly owned subsidiary of the Employees Provident Fund (EPF). The official township site describes it as a mixed development of close to 2,300 acres. The Star, 9 September 2026, reporting a Kwasa Land media day and site tour, used a figure of 912.6 ha, which is consistent with that acreage.
Latest status (checked 27 November 2026): The township sits under both Shah Alam City Council (MBSA) and Petaling Jaya City Council (MBPJ). It is already served by two operating MRT stations, Kwasa Damansara and Kwasa Sentral. At the September 2026 media day, Kwasa Land’s managing director, Datuk Adenan Md Yusof, said completed neighbourhoods, infrastructure, projects under construction, new residential offerings and lifestyle destinations were starting to come together more clearly. This guide covers that official progress, how to reach the township, and a practical checklist for new-home handover and defect inspections.

As at 27 November 2026, Kwasa Damansara is a large township still being built out, with completed neighbourhoods, homes under construction and more projects in the pipeline. Two MRT stations are already open: Kwasa Damansara (KG04 / PY01), the interchange between the Kajang and Putrajaya Lines, and Kwasa Sentral (KG05) on the Kajang Line. If you are buying or taking vacant possession of a new home here, a structured handover walk-through and, if you want one, an independent defect inspection are practical ways to record the condition of the unit.
- Kwasa Land is the master developer of the 912.6 ha township. The September 2026 media day, as reported by The Star, pointed to completed homes such as Dedaun Rimba, projects under construction such as Linari (targeted for 2028), and a wider pipeline on both the Shah Alam and Petaling Jaya sides.
- Kwasa Damansara MRT station and Kwasa Sentral MRT station have been in service since 16 December 2016. Official MRT Corp pages list Park ’N Ride at both stations (500 car bays and 100 motorcycle bays each), operated by a third-party company. Kwasa Sentral’s Entrance B is still listed as closed until the east side of the station is developed (Kwasa Damansara station, Kwasa Sentral station).
- A new-home defect inspection is a dated record of visible issues at handover. It does not, on its own, decide who is responsible for any defect, and it is not a promise about the outcome of a dispute with a developer.
01Latest Status (November 2026)
Status checked 27 November 2026 against the official Kwasa Damansara website, official MRT Corp station pages, and The Star’s 9 September 2026 report of Kwasa Land’s media day and site tour.
Kwasa Land’s public message at that briefing was that the township is moving from masterplan towards a more complete place to live, but that development is still being phased according to infrastructure readiness, market conditions and community needs. The Star quoted Adenan as saying Kwasa Land’s role is not only to deliver individual developments, but to make sure those pieces form a connected community over the long term.
The official site, kwasadamansara.com.my, lists the township office at No. 6, Persiaran Kwasa Perdana, Kwasa Damansara, 40150 Shah Alam, Selangor, with email info@kwasaland.com.my. For the latest project list and sales enquiries, use that official site rather than unofficial listing pages.

Menara KWSP, the EPF headquarters, already stands in the township. The Star described Kwasa Damansara City Centre (KDCC), a 25.9 ha commercial centre next to Menara KWSP, as the emerging business, retail and community core, with Urban Eats already operating beside the headquarters as an early lifestyle offering.
02Township Progress And Projects
The September 2026 site tour, as reported by The Star, focused on the Shah Alam side of the township. The project details below are taken from that report and, where they also appear, from the official township website. This page does not add prices, and it does not treat take-up figures as independently verified beyond the newspaper report.
| Project | Developer | What Was Reported |
|---|---|---|
| Dedaun Rimba | YTL Land and Development | Completed 264-unit scheme on 5.14 ha: 68 three-storey link homes and 196 one-and-a-half-storey townhouses. The Star said it has received its Certificate of Completion and Compliance. The same report said the link homes sold out at the initial sales preview, and that the townhouses recorded an 80 per cent take-up rate on the same day. |
| Daya Residence | TSR Development | 260-unit freehold, low-density scheme in two phases: 34 semi-detached homes, one bungalow, seven town villas and 218 condominium units. The Star did not state a completion date. |
| Linari | Not named as a separate developer in The Star report | Under construction. 496 residential units, including 480 condominium units in two towers and 16 Parkhomes, scheduled for completion in 2028. The official township site also lists 496 units. |
| Tujuh Residences | MRCB | 573 residences in two residential wings, within the 25.9 ha Kwasa Damansara City Centre. The official site describes a 29-storey development offering 573 serviced residences. |
| RIA Residensi | Sunsuria | Next to Linari. Described as MRT-linked freehold homes on 3.84 ha, in two phases, with 520 units (494 condominium units and 26 landed homes). |
| Waringin | Not named in The Star report | A recent addition: 820 homes on 8.53 ha, to be delivered in two phases of terrace homes and four condominium towers. The official site also lists 820 units. |
| Idaman Kwasa Damansara | Affordable housing programme, listed on the official site as Rumah Selangorku (RSKU) Idaman | The Star said Phase 1 comprises 1,669 homes on 5.63 ha, targeted for completion in 2027, with more than 3,400 approved applicants, and that it forms part of a wider plan for 11,000 affordable homes. The official site describes two freehold residential plots of about 39.12 acres for 4,694 RSKU Idaman units, a larger figure that appears to describe more than Phase 1 alone. |
The same Star report listed a further pipeline that was not on the day’s site tour. On the Shah Alam side: Exsim’s D’Nuri and D’Evia, and a new development by PPB Hartabina. On the Petaling Jaya side: ParkCity Damansara Phase 1, known as Zenia, plus projects by Serene Impian, LBS Bina Holdings and Nadi Cergas. The Petaling Jaya side is also planned to host the township’s first international school, to be developed by Educ8, the organisation behind Epsom College in Malaysia. This page has not independently confirmed the current construction or sales status of those pipeline projects.
Population forecasts for the township were not set out in The Star article used as the main news source for this guide. Other 9 September 2026 reports, which the official Kwasa Damansara news page also links to, gave different five-year figures: The Malaysian Reserve was listed as “exceed 60,000”, while Utusan Malaysia and New Straits Times were listed as about 100,000. Because those figures do not agree, this page does not adopt a population target.
03MRT Stations And Access
Public transport is already one of the township’s most concrete advantages. Official MRT Corp pages, checked on 27 November 2026, give the following.
Kwasa Damansara (KG04 / PY01)
Kwasa Damansara station opened on 16 December 2016. It is the interchange between the MRT Kajang Line and the MRT Putrajaya Line, with two elevated island platforms and four platform faces, above a ground-level concourse. The official address is Stesen Kwasa Damansara, Seksyen U4, 40150 Shah Alam, Selangor. The station has two entrances, A and B, on either side of Persiaran Surian. Entrance B is also reachable from Jalan Camar 4/5. Official facilities include lifts, escalators, a surau, shops, ticket vending machines, public toilets, a customer service office and feeder buses. Park ’N Ride is listed as 500 car bays and 100 motorcycle bays, owned and operated by a third-party company. This page does not list a parking rate, because the official station page does not publish one.
The same Kajang Line continues south through Kota Damansara and on to Bandar Utama, where it meets the LRT Shah Alam Line (LRT3). For the current LRT3 station list and transfer rules, see our LRT3 Shah Alam Line guide.
Kwasa Sentral (KG05)
Kwasa Sentral also opened on 16 December 2016. It is a Kajang Line station with side platforms, inside the Kwasa Damansara development and away from the main Jalan Sungai Buloh. Official access is via a road from the Jalan Sungai Buloh–Persiaran Sungai Buloh intersection. The official address is Stesen Kwasa Sentral, Seksyen U4, 40150 Shah Alam, Selangor.
The station was designed with two entrances, but official pages still say that only Entrance A is in use, leading to the feeder-bus stop, taxi lay-by, drop-off area and Park ’N Ride. Entrance B, on the east side, “is currently closed and will be opened when the area on the east side of the Station is developed.” Park ’N Ride is again listed as an open car park with 500 car bays and 100 motorcycle bays, operated by a third party.

Official feeder buses T801, T802, T803 and T804 run from the Entrance A bus hub, linking the station with housing areas in Kota Damansara and Subang. The official T801 page lists a fare starting from RM1.00, a concession fare of RM0.50, a first bus at 6.00 am and a last bus at 11.00 pm, and a frequency of 15 to 30 minutes, with a note that details can vary by route. Check the official feeder-bus pages before you travel.
Official MRT operation hours, also checked on 27 November 2026, say stations on the Kajang and Putrajaya Lines open at 6.00 am daily, unless a special event requires an earlier opening. Last-train and station-closing times vary by station, line, and whether it is a weekday or a Sunday or public holiday. For Kwasa Damansara and Kwasa Sentral, use the official MRT operation hours table rather than an unofficial timetable.
04Roads, Parks And Everyday Access
The Star’s September 2026 report said the township has access to two KTM Komuter stations, Sungai Buloh and Subang SkyPark, and is about four kilometres from Sultan Abdul Aziz Shah Airport in Subang. It also said Kwasa Damansara is connected to six major road and expressway networks, without naming the six in that article. This page does not invent those road names.
Inside the township, the official website highlights a public-realm framework of nine public parks, and a bicycle route and walking track extending over 23.72 km. The Star said about 101.6 ha, or 11 per cent of the township, has been allocated for parks, landscaped areas and other green and open spaces, with walking and cycling routes planned to link neighbourhoods, public transport, parks and lifestyle destinations. Official sustainability notes include low-carbon city initiatives, an integrated stormwater system described as a Bioecods system, and the use of building information modelling (BIM) in township infrastructure. Those are official aspirations and design features, not a claim about current performance.
05Frequently Asked Questions
Where Is Kwasa Damansara?
Kwasa Damansara is in Selangor, on the former Rubber Research Institute land north-west of Kuala Lumpur. It falls under both Shah Alam City Council (MBSA) and Petaling Jaya City Council (MBPJ). The official township office address is No. 6, Persiaran Kwasa Perdana, Kwasa Damansara, 40150 Shah Alam.
Does Kwasa Damansara Have An MRT Station?
Yes. There are two official stations, both open since 16 December 2016. Kwasa Damansara (KG04 / PY01) is the interchange between the MRT Kajang Line and the MRT Putrajaya Line. Kwasa Sentral (KG05) is the next Kajang Line station inside the township. Searches for “MRT Kwasa Damansara” usually refer to the interchange station.
Is Kwasa Damansara Fully Built?
No. As of the September 2026 Kwasa Land briefing reported by The Star, some neighbourhoods are complete, others are under construction, and a further pipeline has been announced on both the Shah Alam and Petaling Jaya sides. Kwasa Land said the township is being developed in phases.
Which Projects Are Completed In Kwasa Damansara?
The Star’s 9 September 2026 report specifically described Dedaun Rimba as a completed development that has received its Certificate of Completion and Compliance. Linari was described as under construction, with completion scheduled for 2028. Other projects were listed without a clear completed-or-not label in that article, so this page does not classify them.
When Will Idaman Kwasa Damansara Be Completed?
The Star, reporting the 9 September 2026 briefing, said Phase 1 (1,669 homes) is targeted for completion in 2027. That is a target, not a confirmed handover date. The official site also lists a larger RSKU Idaman allocation of 4,694 units across two plots.
How Do I Get To Kwasa Sentral MRT Station?
Official MRT Corp pages say access is via a road from the Jalan Sungai Buloh–Persiaran Sungai Buloh intersection, and that only Entrance A is currently open. Entrance B remains closed until the east side of the station is developed. Feeder buses T801 to T804 start from the Entrance A bus hub.
06New-Home Handover And Defect Checks
A township still filling out with new homes is exactly where a careful handover matters. Whether you are taking vacant possession of a landed house, a townhouse or a condominium unit, the practical task is the same: record the condition of the property, clearly and on a dated list, while the finishes are still new and while your rights under the sale agreement are still easy to exercise. This section is general practical guidance. It is not legal advice, and it does not replace the terms of your sale and purchase agreement or any defects-liability arrangements that apply to your unit.
Before or on handover day, it helps to walk the property in a fixed order so that fewer items are missed:
- Confirm that you have the keys, the vacant-possession documents, and, where it applies, that the developer has obtained a Certificate of Completion and Compliance (CCC) for the building. Ask for that confirmation in writing if it is not already in your pack.
- Work room by room. Look for cracks in walls, ceilings and floors; hollow or uneven tiling; gaps at skirting and door frames; doors and windows that stick or do not latch; and scratches or chips in finishes.
- In wet areas, check for staining, poor falls to floor traps, leaking shower trays or basins, and water marks on the ceiling of the room below, if you can see it.
- Test electrical points, lighting, water pressure, sanitary fittings and air-conditioning drainage, and note anything that does not work or that leaves water where it should not be.
- For strata homes, also walk the common areas you will use — lift lobbies, corridors, stairwells and the car park — and photograph anything that already looks unfinished or damaged.
- Photograph each item, with a short written note and the date, and keep a copy of the list you hand to the developer or the joint management body.
An independent building defect inspection is simply a structured version of that walk-through, carried out by an inspector who then sets out the findings in a plain report. The report is a record of what was visible on the inspection date. It does not, on its own, decide responsibility for any defect, and it is not a promise about the outcome of a dispute.
If you are taking handover of a new home in Kwasa Damansara and want an independent record of the unit’s condition, Pro Inspect Solution can carry out a building defect or condition inspection and set out the findings in a written report. For a first conversation, email inspectsolution.pro@gmail.com.
We hope this guide helps you follow the township’s progress and plan a new-home handover with clear eyes. For official project updates, start with kwasadamansara.com.my. For station access and train times, use the official MRT Corp pages linked above.
Sources: Official: Kwasa Damansara website (township description, close to 2,300 acres, nine parks, 23.72 km walking and cycling routes, featured projects, office address); Kwasa Damansara news page (links to September 2026 coverage, including conflicting population figures); Kwasa Damansara MRT Station (opened 16 December 2016, KG04 / PY01 interchange, entrances, Park ’N Ride capacity); Kwasa Sentral MRT Station (opened 16 December 2016, KG05, Entrance B still closed, Park ’N Ride, feeder buses T801–T804); MRT feeder bus T801 (fare starting from RM1.00, first and last bus times); MRT operation hours. News: The Star, 9 September 2026 (912.6 ha, MBSA and MBPJ, media-day project list and unit counts, Idaman Phase 1 target of 2027, two MRT stations, two KTM stations, about four kilometres from Sultan Abdul Aziz Shah Airport, 101.6 ha of parks, KDCC and Menara KWSP). Last updated: 27 November 2026.
Need an independent engineering inspection?
Talk to our engineers about your building, defect or dispute. Email inspectsolution.pro@gmail.com