Understanding the statutory consultancy rates charged by registered consulting engineers is vital for developers, joint management bodies (JMBs), asset owners, and contractors across Malaysia. Governed by regulatory statutes, the engineering scale of fees ensures financial transparency, consumer protection, and strict adherence to structural safety standards in construction, infrastructure, and forensic rehabilitation works.
By Ir Vimal | Published on October 5, 2026 | Updated November 4, 2026
The BEM Scale of Fees is the Board of Engineers Malaysia’s schedule of fees for consulting engineering services, made under the Registration of Engineers Act 1967. It groups works into Type A, B and C, charges a percentage of the cost of works that falls as project value rises, and uses time-based salary multiplier fees for investigations and advisory work.
Related services: Building condition assessment, Expert witness engineer, Periodic building inspection (Section 85A).
Table of Contents
- What is the BEM Scale of Fees?
- Statutory Framework and Legal Basis in Malaysia
- Classification of Works: Type A, Type B, and Type C
- Methods of Fee Calculation
- Fee Scale Percentage Breakdown Based on Project Value
- Milestone Payment Stages and Deliverables
- Additional Engineering Services & Reimbursables
- Relevance to Forensic Inspections and Condition Audits
- Frequently Asked Questions (FAQ)
What is the BEM Scale of Fees?
The Scale of Fees represents the standardized regulatory pricing schedule established by the Board of Engineers Malaysia (BEM). It stipulates the professional fee baselines that registered consulting engineering practices (CEPs) and professional engineers are entitled to charge for statutory civil, structural, and mechanical/electrical consultancy services throughout the country.
This framework was formulated to eliminate predatory price undercutting—a hazardous commercial practice that systematically degrades design thoroughness, supervision quality, and public safety—while safeguarding clients from predatory price gouging. Whether managing greenfield property developments or securing specialized Structural Repair Consultancy for distressed infrastructure, the BEM schedule delivers clear, enforceable fiscal parameters.
Statutory Framework and Legal Basis in Malaysia
Engineering consultancy in Malaysia operates under strict statutory mandates codified in the Registration of Engineers Act 1967 (Act 138) and the Scale of Fees for Consulting Engineering Services, determined by the Board under paragraph 4(1)(d) of the Act (P.U.(B) 548/1998). Under Act 138, only PEPCs and ECPs may submit engineering plans (s8); the PSP and SP roles themselves come from the UBBL, where a PSP may also be a Professional Architect or Registered Building Draughtsman.
These statutory responsibilities directly interface with the Street, Drainage and Building Act 1974 (Act 133) and the Uniform Building By-Laws 1984 (UBBL). Every calculation, structural member specification, storm drainage profile, and foundation design must comply with relevant Malaysian Standards (MS) and British/European codes (such as MS EN 1990 to MS EN 1998 for Eurocode design), placing statutory liability squarely upon the endorsing engineer.
Classification of Works: Type A, Type B, and Type C
SOF 1998 groups the components of the works into three types:
| Type | Covers |
|---|---|
| Type A | Civil and structural engineering works (other than structural works in buildings), and mechanical and electrical engineering works (other than engineering systems in buildings). |
| Type B | Structural engineering works in buildings of more than four storeys. |
| Type C | Engineering systems in buildings of more than four storeys. |
| Housing (4 storeys and below) | Separate Scale of Fees for Housing Development (P.U.(B) 288/1997). |
Housing development of four storeys and below follows the separate Scale of Fees for Housing Development (P.U.(B) 288/1997).
Methods of Fee Calculation
The Board of Engineers Malaysia stipulates two standard fee calculation methodologies depending on procurement arrangements and project scopes:
| Calculation Methodology | Typical Application Scope | Billing Mechanism & Formula |
|---|---|---|
| Percentage of Cost of Works | Standard design-bid-build developments, new superstructures, and major civil infrastructure. | Calculated as a percentage of the total cost of components of the works in each type; BEM’s FAQ notes that fees are computed separately for each type of component and that preliminaries are included in the cost of works. |
| Salary Multiplier (Time-Based) | Forensic defect investigations, dilapidation audits, litigation expert witness, and advisory roles. | Time-based fees under SOF 1998 are computed on salary cost multiplied by a multiplier as defined in the Scale. |
Fee Scale Percentage Breakdown Based on Project Value
For conventional project deliveries, the percentage scale operates inversely to the total construction cost. Larger project sums benefit from economies of scale, as illustrated in the standard BEM reference brackets below:
| Total Cost of Components of the Works in the respective type (RM) | P(max) | P(min) |
|---|---|---|
| RM 100,000 and below | 10.00% | 8.25% |
| RM 1,000,000 | 6.80% | 6.30% |
| RM 10,000,000 | 5.00% | 4.75% |
| RM 100,000,000 | 3.95% | 3.60% |
| RM 1,000,000,000 and above | 2.54% | 2.28% |
The table above is an extract of the SOF 1998 fee table. Intermediate values are interpolated linearly. The percentage between P(min) and P(max) is agreed before engagement, according to the complexity of the work.
Milestone Payment Stages and Deliverables
Consultancy fees are structured around key deliverables rather than arbitrary calendar dates. This safeguards the client's cash flow while ensuring the consulting practice delivers verifiable engineering milestones:
- Preliminary Stage (20%): Conducting topographical appraisals, geotechnical review, preliminary member sizing, and conceptual approvals with local planning departments (OSC / PBT).
- Design Stage (i) (35%): Detailed engineering calculations, preparation of structural tender drawings, and formal endorsement under UBBL by-laws for local council building plan approval.
- Design Stage (ii) (20%): SOF 1998 pays the design stage in two parts. Together they cover preparing designs and tender drawings, and the conditions of contract, specifications, schedules and bills of quantities needed to obtain tenders.
- Tender Stage (5%): Assisting in Bill of Quantities (BQ) formulation, evaluating contractor tender bids, and publishing formal tender assessment reports.
- Construction Stage (20%): Site supervision by Resident Engineers or Clerks of Works, reviewing contractor Requests for Information (RFIs), inspection of reinforcement placement, and sign-offs for concrete casting. SOF 1998 has no separate completion stage; work such as witnessing acceptance tests and issuing the certificates required under the contract falls within this stage.
Additional Engineering Services & Reimbursables
Core percentage fees cover basic design, municipal submission, and periodic site inspection. However, complex projects require specialized ancillary engineering inputs that are billed under separate terms:
- Pre-construction baseline audits such as an authenticated Dilapidation Survey to document pre-existing defects in neighbouring premises prior to vibration-inducing piling works.
- Post-construction buyer handover verification and common property auditing under a professional Property Defect Inspection (DLP), vital for developer accountability under the Strata Management Act 2013 (Act 757).
- Advanced aerial inspections, thermal scanning, and building envelope assessments via Façade & Roof Inspection (Drone) across commercial high-rises.
- Material quality verifications, concrete core sampling, and non-destructive rebound hammer tests overseen by trained and competent technicians.
- Bar bending schedules, charged as an additional 3/4% of the cost of the reinforced concrete work (SOF 1998).
- A co-ordinating fee of 5% of the fee paid to a specialist consultant engaged for the works, where the lump-sum method has not been agreed (SOF 1998).
- Reimbursable disbursements such as printing costs, soil bore-hole subcontracting, and local council plan processing fees.
Relevance to Forensic Inspections and Condition Audits
When investigating cracked retaining walls, roof leakage, or differential ground settlement in existing buildings, applying construction cost percentages is unfeasible. Consulting engineers instead utilize time-based salary multiplier fees or agreed lump-sum quotes.
Mandatory periodic building inspections under Section 85A of the Street, Drainage and Building Act 1974 (Act 133)—which applies to buildings exceeding five storeys aged ten years and older—rely on these salary multiplier models. Reports prepared by a registered engineer can be prepared as expert evidence; whether and how much weight they carry is for the tribunal or court to decide.
Frequently Asked Questions (FAQ)
Are consulting engineers legally bound to charge strictly according to the Scale of Fees?
The BEM Scale of Fees serves as the official regulatory benchmark endorsed by the government and professional bodies. BEM has stated in writing (letters BEM/SOF/01-1 Jld.1 and Jld.1(a), 7 Oct 2022) that offering fees below the BEM Scale of Fees 1998 is a clear contravention of the Act.
How are consulting fees calculated for building defect inspections and repair jobs?
Forensic defect investigations, dilapidation surveys, and repair consultations are rarely tied to builder construction values. They are usually quoted via a fixed lump-sum engineering fee or a time-based fee (salary cost multiplied by a multiplier as defined in the Scale) reflective of technical complexity and equipment mobilization.
Who pays for engineering submission fees to municipal councils in Malaysia?
Statutory processing fees levied by local authorities (such as DBKL, MBPJ, or MBSA) and technical agencies (TNB, Air Selangor, IWK, Bomba) are classified as reimbursable disbursements. These costs are paid directly by the client or invoiced at actual cost by the submitting engineer.
Contact Us / Professional Inspection & Engineering Consultation
Pro Inspect Solution, led by Ir Vimal, Professional Engineer, provides professional building condition assessments, structural integrity audits, handover defect inspections, and professional engineering advisory across Malaysia.
- 📍 Service Coverage: Kuala Lumpur, Selangor, and Nationwide Malaysia
- 📞 Phone / WhatsApp: +60 16-806 4902
- ✉️ Official Inquiries: inspectsolution.pro@gmail.com
- 🌐 Official Website: inspectsolution.pro
- 👷♂️ Lead Engineer: Authored & verified by Ir Vimal
Enquiries
For enquiries about building inspection or engineering consultation, contact Pro Inspect Solution on WhatsApp (016-806 4902).